Lumiar is one of Lisbon’s largest sub-municipal territories, with almost 50,000 residents and marked contrasts between higher-income neighbourhoods and areas of social housing. Many people live in multi-apartment buildings where installing individual solar panels is difficult, while older and thermally inefficient homes leave some households exposed to high bills and poor thermal comfort. Lisbon aims to become climate-neutral by 2030, and the Telheiras/Lumiar Renewable Energy Community (CERT/L) shows how a parish council can turn this city-wide ambition into practical neighbourhood action.
The initiative grew from the 2020 ‘Network of Ideas’, a participatory process organised by the Local Partnership of Telheiras that involved more than 300 residents. One proposal was simple but ambitious: produce renewable energy locally and share it among neighbours. A volunteer working group formed in 2021. The Lumiar Parish Council – sub-municipal local authority – joined as co-promoter, alongside Associação Viver Telheiras, with technical and scientific support from the renewable energy cooperative Coopérnico and CENSE NOVA-FCT (NOVA University of Lisbon).
CERT/L did not create a new company or hand the project to a commercial developer. It built on Associação Viver Telheiras, an established non-profit organisation that now acts as the community’s legal and operating entity. Solar systems are installed on public buildings formally owned by Lisbon Municipality and managed by the Parish Council. They are collectively financed and managed through CERT/L, with the public buildings using electricity first and the remaining production shared through the grid with nearby households, small businesses, condominiums and organisations. Every member, including the local authority and vulnerable households, has one vote in general assemblies.

© Associação Viver Telheiras
What Lumiar is doing
Since 2021, the Lumiar Parish Council has co-promoted CERT/L and later joined as a member and producing participant, linking citizen initiative with public assets. It identified suitable buildings under its management, agreed cooperation protocols with Associação Viver Telheiras and supported the permissions required from Lisbon Municipality. This unlocked the pilot at the former Quinta de São Vicente olive press and the second installation at the Alto da Faia sports hall.
The Parish Council added capacities that a volunteer group could not provide alone. Sustainability and administrative staff supported liaison with municipal departments, national licensing authorities and the electricity distribution system operator. Public rooms and local communication channels supported meetings, recruitment and information sessions. Participation in the Sun4All Community of Practice also helped the authority exchange experience and plan the second phase.
Social inclusion was treated as a public responsibility. Parish social services and trusted partner organisations identify and approach households already receiving support, explain the project and help them apply. Vulnerable households join without upfront investment, pay a much lower annual fee and retain equal voting rights; the extra cost is shared by the Parish Council and regular members. Three vulnerable households entered the pilot, while seven selected for Phase 2 were awaiting final regulatory approval in June 2026.
Public buildings use part of the electricity before the remainder is shared, reducing the Parish Council’s bills rather than creating a commercial revenue stream. On-site savings were estimated at €1,045 by June 2026, while almost all remaining generation was used by members. Energy-poverty support is therefore financed directly through the solidarity mechanism. Lumiar Parish Council President Ricardo Mexia described the project as combining sustainability and a social dimension with interaction and collaboration between citizens.

© Associação Viver Telheiras
Outcomes
By June 2026, CERT/L operated 57 solar panels (32.89 kWp) on two public buildings and had 66 active members. Since sharing began on 21 June 2025, it had allocated 27,355 kWh of local solar electricity, generated an estimated €5,521 in member savings and avoided 1,970 kgCO₂e. Cumulative surplus was only 1%. In June 2026 alone, 5,888 kWh covered 27% of members’ combined consumption and saved an estimated €1,194 (19 euros on average for each member).
Members receive personalised monthly reports showing consumption, shared electricity and estimated savings. A community-developed algorithm processes 15-minute smart-meter data, reduces waste and preserves agreed entitlements; early analysis indicates that vulnerable members achieved around twice the savings produced by conventional allocation approaches. General assemblies, open coordination meetings, energy-bill workshops, advice and guided visits have also strengthened energy literacy and trust.
The project is now a reference for Portuguese communities and local authorities. Its bilingual ten-step Practical Guide and lessons have been shared through European projects, Covenant of Mayors events and study visits. Recognition includes the Parish Council’s Medal of Merit, an honourable mention in Portugal’s LIGAR – Energy for All Award of the National Energy Poverty Observatory, the Sustainability and Innovation Prize of the CASES cooperative (one of the most recognized prizes for the social economy in Portugal), and selection for the €45,000 European Energy Communities Facility programme.
Lessons learnt
The strongest lever was co-production. Residents brought the idea and volunteer commitment; the Parish Council contributed public assets, legitimacy, social-service links and access to public administration; Associação Viver Telheiras provided a trusted legal and community base; and Coopérnico and CENSE NOVA-FCT added technical, financial and scientific expertise. Building on an existing local network reduced costs and supported recruitment.
The project also learnt not to underestimate regulation, data and workload. The pilot took about two years to navigate licensing, while operations later required processing nearly one million data points each month. Dependence on volunteers created fragility. A phased approach helped: start small, document procedures, test governance and allocation rules, then expand. Future phases may require professional capacity without weakening democratic control.

© Associação Viver Telheiras
Next steps
CERT/L is preparing a third phase, with 142 solar panels and 85 kWp installed power, supporting up to 125 new members. The proposed site is the Telheiras Primary School, although final municipal validation is still pending.
With support from the European Energy Communities Facility, a five-year plan explores expansion to 22 additional buildings and more than 3,000 members, alongside storage, electric mobility, energy-efficiency services and renovation. The aim is a durable local energy service that reserves 10–20% of participation opportunities for vulnerable households.
National challenges include slow licensing, regulation poorly adapted to small citizen initiatives and dependence on the distribution system operator for data and contracts. Technological constraints include grid capacity and data quality; financially, larger systems require more upfront capital than member contributions alone may provide.
Locally, success depends on continued access to public roofs, timely coordination with Lisbon Municipality and adequate staff capacity. The Parish Council can protect the social mission through continued co-financing, integration with climate and social planning, and cooperation between sustainability, facilities and social-service teams.
Professionalisation must complement participation. Stable administrative, technical and communication capacity is needed, while general assemblies, open coordination meetings and ‘one member, one vote’ continue to safeguard local ownership.
Replication potential
Lumiar shows that local authorities do not need to create or control an energy company to act. They can provide public roofs, participate as one member among equals, help navigate administration, use social services to reach excluded households and combine public contributions with citizen investment. An established association or cooperative can host the legal and operational structure if community control is protected.
The transferable sequence is: identify a participatory local priority; build a complementary partnership; start with a manageable public building; agree financing and solidarity rules; recruit openly; document licensing; and establish accessible monitoring before scaling. Inclusion must be designed from the outset, including who pays, how households are approached and how confidentiality is protected.
Beyond Portugal, the case shows how public infrastructure can advance climate targets while keeping benefits in the territory. Regulatory routes differ, but the principle is universal: local government can enable citizen leadership rather than replace it.
Lumiar, Portugal
Stage of implementation: Operational

Type of Activities
Energy sharing
Energy production
Energy-efficiency advice and energy literacy
Energy Figures
Total capacity installed: 32.89 kWp (57 solar panels across two public buildings).
Local use of generation: Approximately 99% of the electricity available to the community has been used locally; cumulative surplus was 1% by June 2026.
Bills and energy demand: A uniform percentage reduction in bills has not yet been calculated because tariffs differ. In June 2026, community solar covered 27% of members’ combined electricity use on average, producing €1,194 in estimated savings (€19 per member on average).
Type of support from the Municipality
- Facilitation: setting targets,workshops, and permits
- Support: access to public roofs/land, and administrative support
- Direct involvement: promoter of the energy community
Covenant figures
- Lisbon Municipality is the relevant Covenant signatory; Lumiar is a sub-municipal authority in Lisbon.
- Climate neutrality by 2030 under Lisbon’s Climate City Contract and the EU Mission for 100 Climate-Neutral and Smart Cities; the contract also targets 100 MW of solar capacity by 2030.
Additional information
Funding
Total budget: The project records around €25,000 in cumulative initial member investment and annual fees by June 2026 for the two operational phases. CERT/L also received €45,000 from the European Energy Communities Facility for business planning, professionalisation and scaling.
Sources of funding: Modular contributions from regular members; contributions from the Lumiar Parish Council; annual membership fees for operation and maintenance; solidarity contributions that remove the upfront cost for vulnerable households; and European technical or development support. For the pilot and Phase 2 social memberships, two-thirds of the initial cost was covered by the Parish Council and one-third by regular members. The planned Phase 3 model reverses this split: one-third local authority and two-thirds other members.
Municipal personnel engaged
Three main persons involved – the President of the Lumiar Parish Council, the Board Member for Sustainability, and the technician for Sustainability; other staff from political leadership, sustainability, social services, facilities/asset management and communications have contributed as needed.
Tasks and duration: Co-development, public-building access, social-member identification and support, stakeholder liaison, events and communication since 2021.
Contact
- Project / legal entity: Associação Viver Telheiras – Centro de Convergência de Telheiras | geral@vivertelheiras.pt | https://vivertelheiras.pt/certelheiras/en/
- Local authority: Lumiar Parish Council | info@jf-lumiar.pt | https://jf-lumiar.pt/
- Suggested editorial contacts: Dr. Ricardo Mexia, President of the Lumiar Parish Council, and Miguel Macias Sequeira, Executive Coordinator of CERT/L.