1. Overhaul of secondary schools of I-III grades №6
Druzhkivka City Council. The school is a two-storey building from 1933. The institution has 9 doors blocks and 132 window blocks that need to be replaced by metal-plastic. To ensure the thermal regime and to save heat, it is necessary to insulate facades with an area of 2,769.9 m2 and roof insulation with an area of 2,741.62 m2.
2. Overhaul (rehabilitation) of secondary schools of I-II grades №8 Druzhkivka City Council. The school is a two-storey building from 1962. It has its own gas boiler room. The institution has 6 door blocks and 145 window blocks, which need to be replaced by metal-plastic. To ensure thermal regime and heat sav
Implementation Timeframe: 2018-2019
Sector: Municipal
Implementation Cost: 780.000,00€
GHG Reduction: 128 tonnes