Signatory

2030
|
Mitigation |
||
|
||
|
Adaptation |
||
|
||
|
Energy Poverty |
||
|
Italy
Committed since 2011
|
Maristella Galli
|
||
|
Mayor
|
MAIN CONTACTS
| Clelia Colla |
SUPPORT
Overview
GHG emissions/capita
not available
Achieved Reduction
not available
Key Actions
B-ip 1 complete relamping of public light with led and energy saving oriented management MITIGATION
The action aims to complete the relamping with LED of the whole PL plant.
Implementation Timeframe: 2018-2025
Sector: Municipal
Implementation Cost: 3.090.000,00€
A-pub 1 requalification of public buildings (net zero emission) MITIGATION
The action aims to minimize the heat and electricity needs of Public Buildings (Group 1) aiming at decreasing dependence on natural gas and fossil fuels in general. This objective has long been pursued through the combination of 3 strategies:
1. Energy requalification of building envelopes and air conditioning systems
2. Integration of renewable sources used for the local production of energy for self-consumption
3. Compensation of electricity withdrawals from the grid through the purchase of certified renewable energy.
Implementation Timeframe: 2020-2030
Sector: Municipal
Implementation Cost: 8.410.279,00€
F-mob 5 infrastructures and initiatives for light mobility MITIGATION ADAPTATION ENERGY POVERTY
The action aims to make the municipal territory completely passable by bike or on foot, to reduce the use of the private vehicle in particular for short journeys (less than 10 km).
Implementation Timeframe: 2021-2030
Sector: Buildings
Implementation Cost: 15.002.931,00€
M-ada 1 - adoption and implementation of the new"general urban plan" (lr 24/2017) MITIGATION ADAPTATION
Emilia-Romagna Region has established that the government of the territory must pursue "the sustainability, equity and competitiveness of the social and economic system, and the satisfaction of the fundamental rights of current and future generations related in particular to health, housing and work". This affirms a new vision of urban and territorial planning that makes sustainable development the only reference point for decisions relating to territorial transformations. Article 31 of Law 24/2017 defines PUG as "the planning tool that the Municipality prepares, with reference to its entire territory, to outline the structural invariances and strategic choices of urban planning and developm
Implementation Timeframe: 2020-2050
Sector: Buildings
Implementation Cost: 250.000,00€
M-ada 2 - urban and peri-urban forestation MITIGATION ADAPTATION
The action is oriented towards the Net Zero Emission by 2050, in order to align the SECAP of the Municipality of Collecchio with the European Climate Law. Therefore, the Plan contains a particular focus on the green heritage of the territory, declined through a series of actions in mutual synergy: ADA 2 Urban and Peri-urban Forestation, ADA 3 Monitoring, Protection and Enhancement of Public Green Areas, ADA 4 Improvement of ecological connectivity through infrastructures Green & Blue and NEU1 Municipal absorption plan.
In particular, this action promotes the reforestation of urban and peri-urban areas, without a specific intended use, which are therefore suitable for the creation of permanen
Implementation Timeframe: 2020-2050
Sector: Buildings
Implementation Cost: 1.135.423,00€
M-ada 5 up redevelopment of aqueduct networks to reduce leaks and drinking water withdrawals ADAPTATION
The aim of the action is to tackle the loss of aqueduct networks, which are very high in the municipalities of the Pedemontana Parmense Union. Considering the difference between the cubic meters fed into the network and the cubic meters invoiced, in 2018 Pedemontana Parmense Union had 39% of leaks of all the water injected.
Implementation Timeframe: 2017-2023
Sector: Buildings
Implementation Cost: 1,00€
M-ada 8 improvement of water regulation in ozzano and gaiano ADAPTATION
The action puts in place interventions, carried out or planned, aimed at reducing the hydraulic and hydrogeological risk of inhabited centers, related to the presence of different streams and canals. The realization of these interventions requires working in synergy with the Consorzio della Bonifica Parmense, the Civil Protection, the Emilia-Romagna Region.
Implementation Timeframe: 2011-2023
Sector: Buildings
Implementation Cost: 1.881.000,00€
Energy efficiency retrofit and energy efficiency certification for all public buildings MITIGATION
Energy renovation of schools
Implementation Timeframe: 2013-2020
Sector: Municipal
Implementation Cost: 1.000.000,00€
GHG Reduction: 22 tonnes
Promoting of photovoltaic public plants MITIGATION
photovoltaic plants in private and public buildings
Implementation Timeframe: 2013-2020
Sector: Electricity
Implementation Cost: 2.600.000,00€
GHG Reduction: 615 tonnes
Renewable Energy Production: 1300 MWh
Promoting methane-fuelled vehicles promoting cycling as a transport mode by the construction of off-road bicycle path network MITIGATION
collecchio - sala baganza cycle path
Implementation Timeframe: 2013-2020
Sector: Transport
Implementation Cost: 1.050.000,00€
GHG Reduction: 3248 tonnes
Action Plan
Target 2020
Approval date: 2013-03-22
| DELIBERA DI CONSIGLIO COMUNALE N. 19 DEL 22.03.2013- APPROVAZIONE PAES | it | Download |
|---|---|---|
| ESITO GRUPPI LAVORO - PERCORSO PARTECIPATO PER STESURA PAES | it | Download |
| PIANO D'AZIONE PER L'ENERGIA SOSTENIBILE - COLLECCHIO | it | Download |
Monitoring Report
Latest monitoring Report:
2024
Commitments
| Commitment 2020 | en | Download |
|---|
The signatory’s information in MyCovenant was last submitted in 2024.