Key Actions
Thermal insulation of walls (1800 m2) with mineral wool (min. thickness 100 mm) and XPS polystyrene (min. thickness 70 mm)
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 99.000,00€
Thermal insulation of walls (1000 m2) and roof (350 m2) with mineral wool (min. thickness 100 mm) and XPS polystyrene (min. thickness 70 mm)
Implementation Timeframe: 2023-2026
Sector: Buildings
Implementation Cost: 74.250,00€
Installation of a wind turbine with total capacity of 200 kW in different forms of financing and ownership: public, public-private, private.
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 220.000,00€
Installation of 8 biomass boilers with total capacity of 850 kW in public institutions
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 153.000,00€
Thermal insulation of walls (900 m2) and roof (300 m2) with mineral wool (min. thickness 100 mm) and XPS polystyrene (min. thickness 70 mm)
Implementation Timeframe: 2023-2026
Sector: Buildings
Implementation Cost: 66.000,00€
Thermal insulation of walls (1250 m2) with mineral wool (min. thickness 100 mm) and XPS polystyrene (min. thickness 70 mm), renovation of the roof
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 38.340,00€
Campaign for raise of public awareness about biomass as a renewable energy source, modern methods and equipments of use of the biomass for heating
Implementation Timeframe: 2023-2030
Sector: Buildings
Implementation Cost: 12.000,00€
Renovation of the most driven local roads (approx. 50 km) in Tareuca commune
Implementation Timeframe: 2022-2028
Sector: Buildings
Implementation Cost: 27.500,00€
Installation of solar PV station with total capacity of 1 MW in different forms of financing and ownership: public, public-private, private.
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 850.000,00€
Establishment of solid waste management system that will include:
-separate waste collection system,
-waste transportation system
-waste sorting and recycling systems
-arranging of waste disposal place according national standards
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 134.400,00€
Planting of 250 ha of forests and foreststrips
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 170.500,00€
Action Plan
Target 2030
Approval date: 2023-05-02