Key Actions
Thermal insulation of the House of Culture walls with mineral wool and XPS polystyrene
Implementation Timeframe: 2024-2028
Sector: Buildings
Implementation Cost: 38.000,00€
Thermal insulation of Floreni High School walls with mineral wool and XPS polystyrene
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 122.500,00€
Thermal insulation of building walls at Family Doctors Center with mineral wool and XPS polystyrene
Implementation Timeframe: 2024-2029
Sector: Education
Implementation Cost: 115.320,00€
Promoting thermal insulation of households:
- Banners with information about energy efficiency measures
- Seminars and training sessions with participation from the Agency for Energy Efficiency and financing institutions (EU4Business, commercial banks) to raise awareness
- Other activities
Implementation Timeframe: 2023-2030
Sector: Buildings
Implementation Cost: 7.000,00€
Promoting the use of PV panels through incentives and advertising
Implementation Timeframe: 2023-2030
Sector: Electricity
Implementation Cost: 8.500,00€
Greening of degraded areas, parks, woodlands forests (gaps) sloping areas, pastures about 167 ha
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 32.000,00€
Installation of biomass boilers for public institutions 80 kW
Implementation Timeframe: 2024-2030
Sector: Municipal
Implementation Cost: 25.000,00€
Thermal insulation of about 550 m2 of Floreni Town Hall walls with mineral wool and XPS polystyrene
Implementation Timeframe: 2023-2030
Sector: Buildings
Implementation Cost: 37.400,00€
Installation of solar PV stations with total capacity of 200 kW in different forms of financing and ownership: public, public-private, private.
Implementation Timeframe: 2024-2030
Sector: Electricity
Implementation Cost: 170.000,00€
Thermal insulation with mineral wool and XPS polystyrene
Implementation Timeframe: 2024-2027
Sector: Buildings
Implementation Cost: 104.400,00€
Construction of watsewater treatment plant
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 165.000,00€
Local partnership with poultry farm (Floreni SA company) to produce green energy (biogas) with installation of 0.5 MW
Implementation Timeframe: 2024-2030
Sector: Industry
Implementation Cost: 125.000,00€
Promotion campaign for biomass energy among locals with the following methods:
- banners and fliers with information about biomass and biomass boilers,
- seminars, trainings, school lessons - for raise of awareness among population,
- small grants and subsidies
- other
Implementation Timeframe: 2023-2030
Sector: Residential
Implementation Cost: 11.000,00€
Organization of solid waste management system:
- separate waste collection system
- waste transportation
- waste sorting and recycling (partnership with special companies)
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 142.000,00€
Thermal insulation of building walls of Middle school with mineral wool and XPS polystyrene
Implementation Timeframe: 2024-2028
Sector: Buildings
Implementation Cost: 87.500,00€
An efficient sewage system will avoid the discharge of polluted water into the water table and increase the degree of protection of water and health
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 165.000,00€
Afforestation of at least 163 ha of degraded land for protection purposes and the creation of recreational areas
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 45.000,00€
Rehabilitation and arrangement of the open-air landfill of animal waste from SA Floreni to reduce air and water pollution
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 185.000,00€
Action Plan
Target 2030
Approval date: 2024-05-28
| Decision on SECAP Approval | ro | Download |
|---|---|---|
| SECAP Floreni | ro | Download |
Commitments
| No documents available |
|---|
The signatory’s information in MyCovenant was last submitted in 2024.