Key Actions
03.12.thermal modernization of apartment buildings MITIGATION ADAPTATION ENERGY POVERTY
Comprehensive thermal modernization of 7 apartment buildings, where condominiums were created under the "Energodim" program
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 691.358,00€
06.03.creation of a cellular energy system of the dolyna tс MITIGATION
The proposed project on the creation of a cellular energy networkis aimed at the development of a decentralized intelligent energy system adapted to specific local conditions and energy needs of residents and communities in the Dolyna.
The project provides for the implementation of a number of complex measures of a technical and organizational nature, aimed at the modernization of the energy networks of the territorial community and their transfer to the next level of development, reliability and efficiency to ensure the social well-being of local residents. The implementation of the project will allow to study and in the future to scale the developed and implemented conceptual solutions.
Implementation Timeframe: 2024-2030
Sector: Electricity
Implementation Cost: 4.098.765,00€
A.16. reconstruction of the central square of the city with the creation of "green" islands, cooling zones ADAPTATION
Reconstruction of the central square of the city with the creation of "green" islands, cooling zones
Implementation Timeframe: 2022-2030
Sector: Buildings
Implementation Cost: 2.600.000,00€
03.08.reduction of energy consumption and co2 emissions in the multi-apartment building sector of the city of dolyna by thermal modernization of buildings. MITIGATION ADAPTATION ENERGY POVERTY
Insulation of the walls of the facade and basement in 30 apartment buildings within the framework of the CoMDeP project
Implementation Timeframe: 2015-2018
Sector: Buildings
Implementation Cost: 899.365,00€
A.05.1 repairs of existing water supply and drainage networks ADAPTATION
Major repairs of existing water supply and drainage networks and construction of new routes (see list of mitigation measures)
Implementation Timeframe: 2025-2028
Sector: Buildings
Implementation Cost: 2.666.667,00€
A.19. planning and planting of young trees in the city, timely cleaning of emergency trees ADAPTATION
Planning and planting of young trees in the community, timely removal of emergency trees
Implementation Timeframe: 2022-2030
Sector: Buildings
Implementation Cost: 22.000,00€
Action Plan
Target 2030, Target 2050
Approval date: 2024-07-17
| SECAP of the Dolyna city-territorial community until 2030 | uk | Download |
|---|
Commitments
| No documents available |
|---|
The signatory’s information in MyCovenant was last submitted in 2025.