Key Actions
Adaptation measures in buildings - repair and/or waterproofing ADAPTATION
Regular inspection of community buildings, inventory of buildings with defects and damaged foundations, repair and/or waterproofing.
Implementation Timeframe: 2023-2027
Sector: Transport
Implementation Cost: 260.000,00€
Adaptation measures in buildings - repair or renovation of roofs ADAPTATION
Inspection of the roofs of public transport facilities, inventory of roofs vulnerable to heavy rainfall, hail and strong winds, repair of vulnerable roofs, waterproofing and strengthening.
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 3.000.000,00€
Power supply of five community organizations through pv plants MITIGATION
It is planned to build 5 roof-top or ground-mounted PV systems with an individual peak capacity of 5 kWp. These 5 PV systems can produce about 30 MWh of electricity annually, which, with a certain reserve, is enough to completely meet the electricity demand of the target 5 municipal structures in the baseline year.
Implementation Timeframe: 2020-2025
Sector: Municipal
Implementation Cost: 250.000,00€
Power supply of municipal buildings in settlements through pv installations MITIGATION
It is planned to install a number of autonomous PV systems for municipal structures in rural settlements with annual electricity demand more than 2,500 kWh/year. It is expected that power generation of these PV installations should completely satisfy
baseline electricity demand of these structures, as well as about 20% of heat demand.
Implementation Timeframe: 2024-2028
Sector: Municipal
Implementation Cost: 210.000,00€
Construction of a community commercial pv power plant MITIGATION
It is planned to build and operate a community commercial (gtid-integrated) PV power plant with a capacity of 0.5 MW, the annual production of which will reach about 650 MWh.
Implementation Timeframe: 2023-2025
Sector: Electricity
Implementation Cost: 500.000,00€
Partial and complete thermal insulation of 36 mbshs MITIGATION
It is planned to carry out complete thermal insulation works of 2 MABs and partial thermal insulation works of 34 MABs in order to improve the energy-efficient characteristics of the buildings and reduce energy consumption.
Implementation Timeframe: 2023-2025
Sector: Residential
Implementation Cost: 1.830.000,00€
Energy-efficient modernization of the urban lighting system MITIGATION
It is planned to replace all old and inefficient (mainly high-pressure sodium lamps) lamps in the street lighting system of Alaverdi with modern energy-efficient LED lamps.
Implementation Timeframe: 2016-2025
Sector: Municipal
Implementation Cost: 73.000,00€
Adaptation measures in transport – prevention of rock falls ADAPTATION
Inventory of roads and infrastructure passing through dangerous rockfall sites and implementation of situational change monitoring, repair of damaged and dilapidated retaining walls.
Implementation Timeframe: 2024-2030
Sector: Buildings
Implementation Cost: 850.000,00€
Adaptation measures in waste sector - provision of proper sanitation ADAPTATION
Prevention of "landfill" hazardous liquids/leachate generation and leakage into the environment at the community's solid domestic waste landfill, as well as ensuring proper sanitation at the landfill.
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 365.000,00€
Adaptation measures in water sector – repair or construction of new water lines ADAPTATION
Investigation and detection of defects in existing water lines and water supply systems for irrigation and drinking water, repair of damaged infrastructure or, if necessary, construction of new water lines.
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 1.920.000,00€
Adaptation measures in transport and water sectors - repair and cleaning of storm water drainage systems and culverts ADAPTATION
Ensuring the smooth operation, proper cleaning, prevention and repair of storm water drainage systems and culverts to prevent road blockages due to flooding and to ensure traffic safety.
Implementation Timeframe: 2023-2027
Sector: Buildings
Implementation Cost: 65.000,00€
Adaptation in land use planning sector – creation and maintenance of green zones ADAPTATION
Creation of community green zones or restoration, expansion, provision of water supply and maintenance of existing zones and recreational areas, parks and gardens.
Implementation Timeframe: 2024-2027
Sector: Buildings
Implementation Cost: 220.000,00€
Action Plan
Target 2030
Approval date: 2024-07-15
| Decision of the Council of Elders of Alaverdi | hy | Download |
|---|---|---|
| SECAP of Alaverdi Community | hy | Download |
Commitments
| Commitment 2030 | hy | Download |
|---|---|---|
| Commitment 2030 | hy | Download |
The signatory’s information in MyCovenant was last submitted in 2024.