* k3 thermal modernization of union of the owners of multiple houses “doverie” multi-apartment residential building MITIGATION
A set of works in 2020 on thermal insulation and installation of external walls, a set of works on thermal insulation and installation of the attic and roof, replacement of external doors, replacement of windows in the common areas of the building, modernization of the lighting system in the common areas of the building, replacement of windows and balcony doors in apartments , as well as the installation of Individual Heating System in 2019
Implementation Timeframe: 2019-2020
Sector: Residential
Implementation Cost: 361.090,00€
* k4 reconstruction of sewer pumping stations no. 1,2,3,4,5 in the city of novovolynsk MITIGATION
The reconstruction included the replacement of obsolete pumping units with new KSB Sewatec pumping units, the replacement of existing shut-off valves with a new production of Fabryka Armatur Jafar SA, the replacement of the ventilation system, the reconstruction of the lighting system with the installation of LED lamps, the installation of electrical power equipment and cable ducts. soft start pumps.
Implementation Timeframe: 2018-2019
Sector: Municipal
Implementation Cost: 1.838.180,00€
A 2. reducing wastewater pollution and preventing leakage ADAPTATION
Reconstruction of sewage treatment facilities (overhaul of sand traps, overhaul of primary radial settling tanks, repair of secondary radial settling tanks, repair of aeration tanks, reconstruction of a sludge station, etc.).
Implementation Timeframe: 2022-2030
Sector: Buildings
Implementation Cost: 654.000,00€
A 5. free access to sources of drinking water in the city ADAPTATION
Installation of drinking fountains in public places (qty 10 units)
Implementation Timeframe: 2022-2025
Sector: Buildings
Implementation Cost: 6.544,00€
A 7. comprehensive landscaping and landscaping of the urban area ADAPTATION
Carrying out activities for landscaping the territory of the community and inventory of green spaces, maintenance of green spaces (lawn arrangement, care for shrubs and their rarefaction, watering shrubs and trees). Landscaping services and maintenance of green spaces.
Implementation Timeframe: 2022-2030
Sector: Buildings
Implementation Cost: 2.832,00€
4.01-4.06 energy modernization of multi-apartment residential buildings of condominiums MITIGATION
Energy modernization of multi-apartment residential buildings of condominiums:
"Shakhtar-23" condominium, "Comfort NV" condominium, "Alina-NV" condominium, "My House-NV" condominium, "Bulvar-34" condominium, "Ozerne-25A" condominium
Implementation Timeframe: 2022-2030
Sector: Residential
Implementation Cost: 6.146.393,00€
1.30-1.32 replacement of incandescent lamps with led lamps in public buildings MITIGATION
Replacement of incandescent lamps with LED lamps in public buildings
Implementation Timeframe: 2022-2030
Sector: Municipal
Implementation Cost: 3.256,40€
A.10. carrying out environmental monitoring ADAPTATION
Installation of equipment for an automated air quality monitoring system (qty - 1 unit).
Implementation Timeframe: 2022-2025
Sector: Buildings
Implementation Cost: 7.853,00€
*k1 reconstruction of heat networks using pre-insulated pipes (closing the boiler house of the yuzh-skh district and switching consumers to the boiler house of the 26th quarter and the boiler house of the shakhtersky district on kaurkova street) MITIGATION
Within the framework of two projects, namely the European project "The first step for the transition to the use of renewable energy sources in Novovolynsk" and the socio-economic development project of Ukraine "Reconstruction of heat supply in the South-Eastern district of Novovolynsk" in 2015, 1300 m. heating network and the reconstruction of the heating network was carried out to replace existing pipelines with pipelines using pre-insulated pipes (PIP) with a length of 822 linear meters.
Implementation Timeframe: 2015-2015
Sector: Heat
Implementation Cost: 493.230,00€
* k2 implementation of renewable energy sources (reconstruction with the introduction of energy-saving technologies of the fuel enterprise "novovolynskvodokanal" at 20 pobedy ave.) MITIGATION
In 2017, the administrative and amenity premises of CE Novovolynskvodokanal were disconnected from the district heating network and transferred to heating from renewable energy sources, in particular, the existing heat generator was reconstructed with the installation of a NIBE brand F-1345-60 heat pump of the “water- with a power of 60 kW.
Implementation Timeframe: 2017-2017
Sector: Municipal
Implementation Cost: 55.210,00€
2.1 modernization of the street lighting system MITIGATION
The modernization of the street lighting system provides:
• replacement of all existing lamps on streets, roads and parks with new energy-efficient LEDs with a dimming function, lower power and improved light output in the amount of 3,889 units. ;
• modernization of all old SHUVO (street lighting control cabinet);
• replacement of all existing non-insulated power lines with new 82.75 km long SIPs;
• replacement of emergency supports and supports that are in an unsatisfactory condition with restoration of protective grounding circuits
Implementation Timeframe: 2022-2030
Sector: Municipal
Implementation Cost: 1.540.429,70€
*к5 внедрение комплекса энергосберегающих мероприятий в оош № 7 MITIGATION
Выполнена комплексная термомодернизация ОШ №7:
- утепление наружных стен минеральной ватой 150 мм.
- замена входной двери и окон на энергоэффективные
- утепление цоколя пенополистиролом 80 мм
- утепление крыши минеральной ватой 180 мм
- утепление сквозного прохода минеральной ватой 120 мм
- реконструкция системы отопления (установка новых радиаторов, термодинамических клапанов, новых трубопроводов)
- установка модульного ИТР с погодозависимым регулированием
- установка нового узла учета тепловой энергии
- реконструкция системы вентиляции (установка вентиляционных установок с роторными рекуператорами и водяными калориферами)
- замена внутреннего освещения на светодиодные светильники
Implementation Timeframe: 2018-2020
Sector: Municipal
Implementation Cost: 825.325,00€
*к3 термомодернизация многоквартирного жилого дома осмд «доверие» MITIGATION
Комплекс работ в 2020 году по теплоизоляции и устройству наружных стен, комплекс работ по теплоизоляции и устройству чердака и крыши, замена наружных дверей, замена окон в помещениях общего пользования здания, модернизация системы освещения в местах общего пользования здания, замена окон и балконных дверей в квартирах , а также установка ИТР в 2019 году
Implementation Timeframe: 2019-2020
Sector: Residential
Implementation Cost: 361.090,00€
*к4 реконструкция канализационных насосных станций №№1,2,3,4,5 в г. нововолынск MITIGATION
Реконструкция предусматривала замену устаревших насосных агрегатов новыми насосными агрегатами марки Sewatec фирмы KSB, замена существующей запорной арматуры на новое производство Fabryka Armatur Jafar SA, замена системы вентиляции, реконструкция системы освещения с установкой светодиодных светильников, установка электросилового оборудования и кабельнопровода. насосами с функцией плавного запуска.
Implementation Timeframe: 2018-2019
Sector: Other
Implementation Cost: 1.838.180,00€
*к1 реконструкция тепловых сетей с использованием предварительно изолированных труб (закрытие котельной юж-сх района и переключение потребителей на котельную 26-го квартала и котельной м-н шахтерский по ул. кауркова) MITIGATION
В рамках двух проектов, а именно Европейского проекта "Первый шаг для перехода на использование возобновляемых источников энергии в Нововолынске" и проекта социально-экономического развития Украины «Реконструкция теплоснабжения Юго-Восточного района г. Нововолынск» в 2015 году было реконструировано 1300 м.п . тепловой сети и выполнена реконструкция теплосети по замене существующих трубопроводов на трубопроводы с использованием предварительно изолированных труб (ПИТ) протяженностью 822 п.м.
Implementation Timeframe: 2015-2015
Sector: Heat
Implementation Cost: 493.230,00€
*к2 внедрение возобновляемых источников энергии (реконструкция с внедрением энергосберегающих технологий топливного предприятия "нововолынскводоканал" жко нмр по пр-ту победы, 20) MITIGATION
В 2017 году административно-бытовые помещения КП «Нововолынскводоканал» были отключены от сети централизованного теплоснабжения и переведены на отопление от возобновляемых источников энергии, в частности, была выполнена реконструкция существующей теплогенераторной с установкой теплового насоса фирмы NIBE марки F-1345-60 типа «вода- мощностью 60 кВт.
Implementation Timeframe: 2017-2017
Sector: Other
Implementation Cost: 55.210,00€
Action Plan
Target 2020
Approval date: 2014-04-29
| Adhesion form | en | Download |
|---|---|---|
| City_Council_decision | en | Download |
| SEAP of Novovolynsk | uk | Download |
Commitments
| Commitment 2050 | uk | Download |
|---|
The signatory’s information in MyCovenant was last submitted in 2023.